William Avenue Mill & Overlay
Schedule/Construction Activity
August 25: Pavement Milling (2-inches). No on-street parking during milling. – 1 day
August 26: Concrete Removals / Prep – 2 days
August 31: Concrete Pedestrian Ramp & Curb/Gutter Work begins, 3-5 days
Sept. 14: Paving (tentative date), 1-2 days
Please use Caution
Watch for construction crews, uneven surfaces, trucks hauling, temporary street parking restrictions, and impacts to pedestrian crossings.